CDM 2007 designers
For information about the role of designers under the 2015 CDM regulations see CDM 2015 designers.
The text below relates to the superseded 2007 CDM regulations and is provided as a historical reference.
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure health and safety issues are properly considered during a project’s development so the risk of harm to those who have to build, use and maintain structures is reduced.
They were introduced in 1994 and came into force on 31 March 1995. They were substantially revised in 2007.
The regulations impose duties on:
- The client.
- Designers.
- The CDM co-ordinator.
- The principal contractor.
- Contractors.
- Workers.
The regulations define a designer as ‘…any person (including a client, contractor or other person referred to in these Regulations) who in the course or furtherance of a business:
relating to a structure or to a product or mechanical or electrical system intended for a particular structure, and a person is deemed to prepare a design where a design is prepared by a person under his control.'
Where ‘design’ includes ‘…drawings, design details, specification and bill of quantities (including specification of articles or substances) relating to a structure, and calculations prepared for the purpose of a design’.
The duties of designers include:
- Ensuring the client is aware of their duties under the regulations.
- In so far as is reasonably practicable, avoiding foreseeable risks to the health and safety of any person that is: carrying out construction work; liable to be affected by such construction work; cleaning any window or any transparent or translucent wall, ceiling or roof in or on a structure; maintaining the permanent fixtures and fittings of a structure; or using a structure designed as a workplace.
- Eliminating hazards which may give rise to risks.
- Reducing risks from any remaining hazards.
- Giving collective measures priority over individual measures.
- Taking account of the provisions of the Workplace (Health, Safety and Welfare) Regulations 1992 which relate to the design of, and materials used in, the structure.
- Take all reasonable steps to provide sufficient information to the client, other designers and contractors.
Where projects are notifiable under the regulations (projects which last more than 30 days or involve more than 500 person-days of construction work), the additional duties of designers include:
- Ensuring a CDM co-ordinator has been appointed for the project. NB It is generally accepted that ‘design’ commences at concept design stage, and so designers should not commence this stage until a CDM co-ordinator has been appointed.
- Take all reasonable steps to provide sufficient information to assist the CDM co-ordinator to comply with their duties, including duties in relation to the health and safety file.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Microcosm of biodiversity in balconies and containers
How minor design adaptations for considerable biodiversity benefit.
CIOB student competitive construction challenge Ireland
Inspiring a new wave of Irish construction professionals.
Challenges of the net zero transition in Scotland
Skills shortage and ageing workforce hampering Scottish transition to net zero.
Private rental sector, living standards and fuel poverty
Report from the NRH in partnership with Impact on Urban Health.
.Cold chain condensing units market update
Tracking the evolution of commercial refrigeration unit markets.
Attending a conservation training course, personal account
The benefits of further learning for professsionals.
Restoring Alexander Pope's grotto
The only surviving part of his villa in Twickenham.
International Women's Day 8 March, 2025
Accelerating Action for For ALL Women and Girls: Rights. Equality. Empowerment.
Lack of construction careers advice threatens housing targets
CIOB warning on Government plans to accelerate housebuilding and development.
Shelter from the storm in Ukraine
Ukraine’s architects paving the path to recovery.
BSRIA market intelligence division key appointment
Lisa Wiltshire to lead rapidly growing Market Intelligence division.
A blueprint for construction’s sustainability efforts
Practical steps to achieve the United Nations Sustainable Development Goals.
Timber in Construction Roadmap
Ambitious plans from the Government to increase the use of timber in construction.
ECA digital series unveils road to net-zero.
Retrofit and Decarbonisation framework N9 launched
Aligned with LHCPG social value strategy and the Gold Standard.
Competence framework for sustainability
In the built environment launched by CIC and the Edge.
Institute of Roofing members welcomed into CIOB
IoR members transition to CIOB membership based on individual expertise and qualifications.
Join the Building Safety Linkedin group to stay up-to-date and join the debate.
Government responds to the final Grenfell Inquiry report
A with a brief summary with reactions to their response.